From free consult to handed-over project — no mystery, no missing weeks.
We visit your Simi Valley home, measure, listen, discuss options and realistic budget. No sales pitch.
Scope, specs, finish list, fixed-price bid. No surprises.
10% deposit, scheduled start date, milestone calendar.
Simi Valley Building Division handles all permit review in-house. Long-lead materials ordered.
Dust-seal, protect paths, remove existing, haul debris same day.
Plumbing, electrical, HVAC. In-house lead coordinates all trades.
Interior finishes start going in.
Cabinets first, countertops templated once cabinets set. 10–14 business days fabrication.
Tile work, appliances, plumbing fixtures, lighting, hardware.
City final inspections — plumbing, electrical, mechanical, building.
Final walkthrough, punch list resolution, warranty documents.